go to top scroll for more

Projects


Projects: Projects for Investigator
Reference Number NIA_NGN_046
Title Biomethane Connection Guidelines
Status Completed
Energy Categories Fossil Fuels: Oil Gas and Coal(Oil and Gas, Refining, transport and storage of oil and gas) 100%;
Research Types Applied Research and Development 100%
Science and Technology Fields ENGINEERING AND TECHNOLOGY (Mechanical, Aeronautical and Manufacturing Engineering) 100%
UKERC Cross Cutting Characterisation Not Cross-cutting 100%
Principal Investigator Project Contact
No email address given
Northern Gas Networks
Award Type Network Innovation Allowance
Funding Source Ofgem
Start Date 01 October 2013
End Date 31 March 2014
Duration 6 months
Total Grant Value £87,000
Industrial Sectors Manufacturing
Region Yorkshire & Humberside
Programme New and Renewable Gas Sources
 
Investigators Principal Investigator Project Contact , Northern Gas Networks (100.000%)
Web Site http://www.smarternetworks.org/Project/NIA_NGN_046
Objectives

The project has the following objectives:
  • To accelerate progression of the Howden project supporting with gas specific expertise
  • To liaise between NWL and NGN to ensure hurdles are overcome quickly and NGNs interests are maintained
  • To develop a user guide to bio-methane injection - This guide needs to be broken down into what is to be covered i.e:
    1. Gas Compression - learning from the Skipton project putting in the first live compression system and its operation over a 12 month period
    2. Siloxanes - Aspects of removal and compliance with HSE requirements
    3. Oxygen level
    4. Design criteria - meeting or modifications to IGEM/TD/16

To provide the Networks and suppliers/operators of waste treatment biomethane plants with the first user guide and best practice recommendations for connection to the gas distribution network with the requirements of that plant in relation to minimum/maximum connection, gas odourisation, dewpoint, gas quality measurement etc. To allow consistency across the gas industry for the benefit of suppliers/operators of biomethane installations and gas distribution network operators.

Expected Benefits:

  • Consistent assessment of requirements of waste treatment gas plants for connection to the gas distribution network. This will ensure a secure and reliable gas supply.
  • Enable cost savings for the both the network operator and the waste treatment gas producer by having common agreed connection guide. Reducing the time in planning, designing and installing renewable gas production from this source.
  • To produce a single simple document for use within Biomethane gas sector that guides and informs both the networks and the produces on all aspects of introducing a successful project.
  • To produce a report detailing all technical aspects of the Howdon treatment works project and how this informed the production of the guide demonstrating the use of a guide help reduce the time to delivery.
Abstract Networks want to facilitate and encourage new sources of gas to enter our networks that meet quality standards, and where necessary adapt quality standards to facilitate the new sources of supply and minimise investment on major infrastructure. At present, produces have no experience or best practice guide to help them through the installation and management of biogas connections. Networks have a variety of policies and procedures to undertake entry connections but these are limited to the transmission system.

As a result of this project with NWL documented guides will be produced as each side goes through installation process. A specialist gas consultant will be employed over the duration of the project to capture all the learning and experiences from a producers and network perspective and document these stages including:
  • Initial Enquiry from Gas Producer/Developer
  • Gas Producer/Developer to place order for the design or design and build
  • Undertake construction phase for all work elements, including any NROs for u/p connection and commissioning up to ECV upstream of ROV
  • Handover process to Gas Network
  • Other Considerations.
Publications (none)
Final Report Northern Gas Networks (2015).Biomethane Connection Guidelines - Closedown Report. NIA_NGN_046_CL_3920 (PDF 59 KB)
Added to Database 07/10/16